Budgetary cost study
A scenario-based conceptual budget for every indexed ELV solution across the Waldorf Astoria hotel and the Boulevard North-West assets. Figures in SAR — planning allowances, not supplier quotations.
From direct cost to budget total
Preliminaries 8%, contingency 20%, commercial markup 15% and VAT 15% applied in sequence.
Where the budget goes
Every solution, fully built up
33 included packages, grouped by solution family. Open any line to see its full price build-up from supply to VAT, its scope basis and source BOQ.
VMS/NVR, IP cameras, storage, analytics where specified, license/retention.
BOQ_CCTV_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Fire alarm panels, field devices and relevant evacuation interfaces; approved Civil Defense criteria.
BOQ_Fire_Alarm_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Doors, readers, controllers, credentials, interfaces, alarm sensors.
BOQ_Access_Control_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Fire alarm panels, field devices and relevant evacuation interfaces; approved Civil Defense criteria.
BOQ_Fire_Alarm_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
VMS/NVR, IP cameras, storage, analytics where specified, license/retention.
BOQ_CCTV_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Security/entrance intercom, stations, integration with ACS.
BOQ_Intercom_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Doors, readers, controllers, credentials, interfaces, alarm sensors.
BOQ_Access_Control_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Fireman intercom/telephone stations and controllers.
BOQ_Firefighter_Telephone_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Security/entrance intercom, stations, integration with ACS.
BOQ_Intercom_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Shared platform/servers/UPS for security; verify platform overlap.
BOQ_Security_Common_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Accessible bathroom call and annunciation system.
BOQ_Disabled_Toilet_Alarm_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Gas detectors and panel interfaces; hotel index only.
BOQ_Gas_Detection_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Fireman intercom/telephone stations and controllers.
BOQ_Firefighter_Telephone_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
MDF/IDF, backbone/fibre, passive Cat6A and active LAN/WLAN; model quantities and network design missing.
BOQ_ICT_Data_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Cable pathways/trays/racks interfaces; coordinate divisions and avoid duplication.
BOQ_ELV_Common_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Indoor cellular coverage/DAS; operator coordination and survey required.
BOQ_GSM_DAS_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
MDF/IDF, backbone/fibre, passive Cat6A and active LAN/WLAN; model quantities and network design missing.
BOQ_ICT_Data_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
IP telephony/PBX, endpoints, gateways and integration; hotel only indexed.
BOQ_Telephone_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Cable pathways/trays/racks interfaces; coordinate divisions and avoid duplication.
BOQ_ELV_Common_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Scene controls, DALI/KNX or other approved protocol, dimming panels, interfaces.
BOQ_Lighting_Control_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
BMS servers, gateways, controllers, trend/alarm points, dashboards.
BOQ_BMS_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Energy and BTU monitoring, meter gateways, BMS integrations.
BOQ_Metering_and_Energy_Management_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
BMS servers, gateways, controllers, trend/alarm points, dashboards.
BOQ_BMS_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Scene controls, DALI/KNX or other approved protocol, dimming panels, interfaces.
BOQ_Lighting_Control_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Garage sensors, ventilation trigger/controls and integration.
BOQ_Parking_Ventilation_Sensors_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Energy and BTU monitoring, meter gateways, BMS integrations.
BOQ_Metering_and_Energy_Management_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Garage sensors, ventilation trigger/controls and integration.
BOQ_Parking_Ventilation_Sensors_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Guest-room automation interfaces, controllers and BMS/PMS links; Assets scope unconfirmed as GRMS.
BOQ_Home_Automation_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Guest-room automation interfaces, controllers and BMS/PMS links; Assets scope unconfirmed as GRMS.
BOQ_Home_Automation_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Master time/synchronization clocks; Hotel index only.
BOQ_Clock_System_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Barrier arms, parking guidance/payment/access where indicated.
BOQ_Parking_Control_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Barrier arms, parking guidance/payment/access where indicated.
BOQ_Parking_Control_Assets.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
EV charging hardware, control and load management, electrical interface by others.
BOQ_EVC_Hotel.xlsx
LOW - UNVERIFIED — conceptual allowance, no source quantities
Unpriced scope awaiting confirmation
18 building/system combinations have no indexed BOQ rows and are excluded from the totals above until the owner/consultant confirms BOQ, drawings and interface boundaries.

- Preliminary conceptual allowances only; final BOQs, drawing take-offs, equipment schedules and approved brands are required to firm up pricing.
- Low and high are scenario multipliers (×0.7 / ×1.5), not statistically derived bounds.
- Excluding 18 zero-indexed combinations does not establish contractual absence — verify before final pricing.